Glen Abber Primary School
Value - £330,000 Duration – 32 Weeks
Principal Contractor – Kier Construction
Procurement – Partnered
New Primary school, Full electrical & mechanical installation Including LV distribution, LV power, LV lighting, New plant room, Domestic water Services, Heating system, Drainage.
Chester zoo –Lion Enclosure
Value -£125,000 Duration 30 Week
Procuremnet Partnered
New installation of electrical power & lighting & electrical heating systems to the new azteck lion enclosure
Highways England national regional controls Centers
Value -£550,000 completes in 52 weeks
National contract for 7 sites
Principle Contractor –kier Specialist Projects
Design & install Critical Power Systems within regional control centres including Generators ,UPS ,BMS systems
Surface Transforms –full Factory internal fit out
Value - £550,000 Duration – 20 weeks
Principal Contractor – Heywood Electrical
Procured
Installation of new Hv Transformer Installation of New 6500 AMP Distribution system throughout production area, installation of furnace, and ancillaries
Contenur – Full factory internal fit out
Value -£620,000.00 Duration 12 months
Principle Contractor- HeywoodElectrical
Procured
Electrical Installation of infrastructure Power & lighting for a new production facility full Turnkey package including HV ,LV
St Michaels C of E School Crosby
Value -£225,000.00 Duration 6 weeks
Principle Contractor-Heywood electrical
Installation of new fire detection system throughout the school
Soulthlands court RLIP –Assisted Living
Value - £135,000.00 Duration – 8 weeks
Principal Contractor – Novus property solutions
Procured
Upgrade of Distribution Power & lighting Systems, Upgrade of heating systems to communal areas
St lukes court –Assisted living RLIP
Value -£137,000.00 Duration 10 weeks
Principle Contractor-Novus property solutions
Procured
Upgrade of Distribution Power & lighting Systems, Upgrade of heating systems to communal areas
Willowdene court RLIP-Assisted Living
Value -£142,000.00 Duration 10 weeks
Principle Contractor-Novus property solutions
Upgrade of Distribution Power & lighting Systems, Upgrade of heating systems to communal areas
St margarets Court RLIP –Assisted Living
Value - £152,000.00 Duration – 8 weeks
Principal Contractor – Novus property solutions
Procured
Upgrade of Distribution Power & lighting Systems, Upgrade of heating systems to communal areas
Whiteways Court Nottingham –Assisted living RLIP
Value -£338,000.00 Duration 10 weeks
Principle Contractor-Novus property solutions
Procured
Upgrade of Distribution Power & lighting Systems, Upgrade of heating systems to communal areas
Sandfield hey RLIP-Assisted Living
Value -£164,000.00 Duration 10 weeks
Principle Contractor-Novus property solutions
Upgrade of Distribution Power & lighting Systems, Upgrade of heating systems to communal areas
Broad oak hospital –Secure Unit
Value - £550,000000 Duration – 26 weeks
Principal Contractor – Avenin
Procured
Refurbishment of secure wards, Installation of new power & lighting, ventilation domestic hot water & heating systems
Liverpool Heart & chest Hospital
Value -£120,000.00 Duration 12 weeks
Principle Contractor-heywood electrical
Procured
Upgrade of electrical switchgear & distribution equipment, replacement of lighting to LED including emergency lighting within the wards
Royal Bolton Hospital –Endoscopy Modular Building
Value -£1.2,0000.00 Duration 52 weeks
Principle Contractor-MTX
Full electrical installation carried out by our projects team, Including UPS/IPS Systems Theatre lighting & power, Switchgear & BMS systems
Jack Mcann Court
Value - £1.1 MILLION Duration – 36 weeks
Principal Contractor –Novus property solutions
Decarbonization scheme –Install PV Battery storage system Install heat pumps and new plant room, To provide heating system to the building rewire power & lighting, With occupied tenants.
DHL Trade Team Knowsley
Value - £120 k Electrical Duration – 4 weeks
Design & Install new LED inelegant lighting system to both warehouse and office areas
Electrical Installation for Bolton Council Wellspring Building
Bolton Council commissioned electrical infrastructure upgrades at the Wellspring Building to support increased capacity and resilience of supply. The project involved the installation of a new 800A power supply, new switched fused isolators, a 1250A main switchboard, heavy-duty containment systems, and new high-capacity cabling.
View ProjectElectrical Installation for New Refrigeration Plant
The project involved the design, supply, and installation of the electrical infrastructure for two new refrigeration plants at sister chicken processing facilities. Each site required a robust electrical installation to support the heavy-duty refrigeration systems essential for poultry storage and processing
View ProjectComplete Electrical Installation for Continor Injection Moulding Factory
Continor, a new factory located in Knowsley Industrial Park, specialises in injection moulding and the manufacture of plastic bins. To support high-capacity production and ensure resilient electrical distribution, a comprehensive electrical infrastructure was designed and installed. The project encompassed HV distribution, transformer installation, LV distribution, and extensive power and containment systems.
View ProjectTurnkey Installation of Emergency Backup Generator at Adhaly Foods Cold Store,Warwickshire
Adhaly Foods Cold Store in Warwickshire required a resilient emergency backup power system to protect critical cold storage facilities. A turnkey solution was delivered, including the supply and installation of a 250 kVA Cummins generator, automatic transfer switch, essential switchboard,containment, and associated cabling infrastructure.
View ProjectEnergy-Saving Lighting Installation at Poppys Europe Warehouse Facility
Poppys Europe, a leading logistics and distribution company, required an energy-efficient lighting upgrade at their warehouse facility. The aim of the project was to improve visibility, enhance forklift operator safety, and reduce energy consumption through smart lighting control systems.
View ProjectJack McCann – Decarbonisation Works
Location: Jack McCann Court, Trafalgar St, Rochdale, OL16 2EE
Completed: March 2024
Project Value: £1.1 million